Home > Latest News > Transport > Corporation Road Bridge update: Footpath closures and weekend working in July 2024

Corporation Road Bridge update: Footpath closures and weekend working in July 2024

Chris

7/3/2024 11:02:45 AM

Transport

4 mins read

Works to Grade II listed structure, Corporation Road Bridge, have been progressing.

 

Application of the primer and paint coatings has also been ongoing along with required preparation works and inspections. Control room works are in progress and all rotten timbers have now been replaced and corroded steels are due to be replaced. Insulation works are complete and roof replacement works will commence soon.

 

Mechanical preparation works to the underdeck of the bridge on Spans 1 to 4 are complete and painting is in progress on spans 1 to 3. To take advantage of anticipated low tide levels, weekend working is required. Footpath closures are also required whilst works are taking place adjacent to public areas to ensure the safety of both the public and the contractor.

 

Footpath closures will take place between 9am and 4pm each weekday. The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

 

July 2024 weekend working and footway closure dates

Footway closures:

Wednesday 3 July

Wednesday 10 July

Thursday 11 July

Wednesday 17 July

Wednesday 24 July

Thursday 25 July

 

Weekend working:

13 and 14 July

 

North East Lincolnshire Council, its delivery partner, Equans and contractor, Spencer Group, would like to thank the public for their patience whilst the work is being undertaken.

 

As Corporation Road Bridge is a construction site, it is important that the public respect the access restrictions in place, which have been introduced for safety reasons.  Members of the public are reminded to please stay outside of all encapsulated and other working areas for their own safety, as well as that of those working there.

 

Visit InvestNEL | Corporation Road Bridge Major Restoration - InvestNEL to keep up to date with the Corporation Road Bridge works.

Other Articles You Might Like

Chris

7/18/2025 10:49:48 AM

Progress Continues on Charterholme Eastern Access and Tritton Road Improvements
Construction work on the eastern access, including the vehicular bridge, to the Charterholme development site is progres...
Business 4 min read

Chris

7/21/2024 9:29:29 PM

Rain Gardens are a colourful way to help reduce risk of flooding in Grimsby.
FROM simple grass verges to flood-mitigating ‘rain gardens’ – an innovative way to see water from heavy downpours drain ...
Business 4 min read

Chris

8/28/2024 7:23:04 AM

Corporation Road Bridge update: Footpath closures and weekend working in September 2024
Works to Grade II listed structure, Corporation Road Bridge, have been progressing.
Business 3 min read

Chris

6/25/2025 10:32:58 AM

Over 6000 flowers planted to commemorate VE Day during Armed Forces Week
A plethora of plants and flowers have bloomed in Cleethorpes to commemorate the 80th anniversary of VE Day during Armed ...